Infrastructure and Services is seeking to engage one or two Professional Services Contractor(s) to provide the Project Manager Resources for the Newcastle Light Rail (NLR) Project for a 12 month contract with the options of a further 12 month plus 6 month periods. The two roles are expected to be Newcastle based for the majority of the engagement period.
The key deliverables of the 2 x Project Manager role are:
- Manage the project delivery of the Newcastle Light Rail Project to the highest industy standards, on time and within budget;
- Provide, lead, control and co-ordinate the resources necessary to provide the Services;
- Project cost tracking and control;
- Update the Project plan;
- Regular reporting to the Principal; and
- Any other activities as instructed by the Principal.
Location
RFT Type
Tender Respondents
Business Name | Trading Name | Address |
---|---|---|
Agonis Group Pty. Ltd. ATF Agonis Group Trust | Agonis Group | 21 Karma Avenue Malvern East VIC 3145 AUSTRALIA |
2XM/TRUWAY (JV) Pty Ltd | - | Level 17 - 31 Market Street Sydney NSW 2000 AUSTRALIA |
APP Corporation | APP Corporation Pty Ltd | Level 2, 426 King Street NEWCASTLE NSW 2300 AUSTRALIA |
Artifex Management Group | - | Suite 302, 410 Elizabeth Street Surry Hills NSW 2010 AUSTRALIA |
Australian Utility Solutions | - | 149 Condamine Street sydney NSW 2093 AUSTRALIA |
Baz Rail Services Pty Ltd | - | 58 Regency St Brighton QLD 4017 AUSTRALIA |
Blue Visions Management Pty Ltd | bluevisions | Level 14 99 Mount Street NORTH SYDNEY NSW 2060 AUSTRALIA |
Eda Project Management Pty Ltd | EDA Project Management Pty Ltd | 5 Messara Cct Durack Qld Brisbane QLD 4077 AUSTRALIA |
EDC Consulting Pty Ltd | - | 155 Bennetts Road Norman Park QLD 4170 AUSTRALIA |
Engenicom | - | 161 King Street Newcastle NSW 2330 AUSTRALIA |
G and K Construction Services | - | 12 Sea Breeze Place Boambee East NSW 2452 AUSTRALIA |
InfraSol Group Pty Ltd | - | Suite 3, Level 2, 65 York Street Sydney NSW 2000 AUSTRALIA |
Infrastructure Services Group Pty Ltd | ISG Projects | 33-35 Ainslie Place Canberra ACT 2601 AUSTRALIA |
IROS | IROS Professional Rail Services | 27, Rani Close Speers Point NSW 2284 AUSTRALIA |
Link Project Management | - | 4 Carre St Elsternwick VIC 3185 AUSTRALIA |
MetaPM Pty Ltd | MetaPM | Level 3, 420 Collins street Melbourne VIC 3000 AUSTRALIA |
North Projects Pty Ltd | North Projects Pty Ltd | Level 7, 75 Miller Street North Sydney NSW 2060 AUSTRALIA |
Projence | - | 3 Alloway Circuit Largs NSW 2320 AUSTRALIA |
Rail Planning Services Pty Ltd | - | Suite 702 91 Phillip Street Parramatta NSW 2150 AUSTRALIA |
Ranbury Management Group | - | Level 18, 270 Adelaide Street Brisbane QLD 4000 AUSTRALIA |
Siecap | Siecap | Level 17, 300 Adelaide Street Brisbane QLD 4000 AUSTRALIA |
SJT Consulting | - | 12 Kanangra Street Warners Bay NSW 2282 AUSTRALIA |
Tactix Group Pty Ltd | Tactix Group | Level 1, 156 Clarence Street SYDNEY NSW 2000 AUSTRALIA |
Tracey Brunstrom & Hammond Pty Ltd | TBH | Level 12, 15 Blue Street North Sydney NSW 2060 AUSTRALIA |
TREMS Consulting | TREMS Consulting | 9 Evergreen Court Parkwood QLD 4214 AUSTRALIA |
Triomf Pty Ltd | Triomf Professional Services | 3/257 Leitchs Road Brendale QLD 4500 AUSTRALIA |
Wabtec Control Systems Pty Ltd | - | 371 Macarthur Avenue Hamilton QLD 4007 AUSTRALIA |
Project Services International Pty Limited | - | Level 23, Governor Phillip Tower 1 Farrer Place Sydney NSW 2000 AUSTRALIA |
Related Records
- Contract Award Notices:
- ISD-16-5091A Projence Pty Ltd
- ISD-16-5091B Engenicom Pty Ltd
Address for Lodgement
Conditions for Participation
The minimum requirements for this Tender are set up as below:
Project Manager - Enabling works and Road Works
Minimum Requirement 1: Evidence that the Tenderer's key personnel has successfully managed road work projects in a CBD environment, valued at over AU$20,000,000 in the last 5 years, including road alteration and improvement works and intersection re-configuration.
Minimum Requirement 2:Relevant tertiary qualification in construction, engineering or project management.
Minimum Requirement 3: Evidence of a minimum of 10 years project management experience in delivering major urban linear infrastructure projects and rail projects.
Project Manager - Procurement and Delivery of the Fixed Infrastructure Contract
Minimum Requirement 1:Evidence that the Tenderer's key personnel has successfully managed a multi-disciplinary rail infrastructure project valued at over AU$40,000,000 in the last 5 years, involving the following techincal disciplines: track, civil and structural, HV and LV reticulation, substations, overhead wiring, communication and control systems.
Minimum Requirement 2: Relevant tertiary qualifications in construction, engineering or project management.
Minimum Requirement 3: Evidence of a minimum of 10 years project management experience in delivering major urban linear infrastructure projects and rail projects.