Transport for NSW (Transport Infrastructure Projects) / Batemans Bay Bridge Commercial Advisor - BOOT and D&C Contracts Management Support - RMS.14.2166.0530-0006

Contract Award Notice ID RMS.14.2166.0530-0006
Publish Date 16-Aug-2017
Category Public Utilities and Public Sector Related Services
Agency Transport for NSW (Transport Infrastructure Projects)
Particulars of the goods or services to be provided under this contract
Batemans Bay Bridge Commercial Advisor - BOOT and D&C Contracts Management Support
Contract Duration 4-May-2017 to 30-Apr-2020

Contract Award Notice Details

Contractor Name WORLEY CONSULTING PTY LTD
ACN 098008818
ABN 50 098 008 818
Is an Aboriginal or Torres Strait Islander owned business No
Street Address Suite 2 8-14 Telford Street
Town/City Newcastle
State/Territory NSW
Postcode 2300
Country AUSTRALIA


Other private sector entities involved in, with an interest in or benefiting from this contract
N/A
Estimated amount payable to the contractor (including GST)

$1,565,124.00 (A project to be undertaken)

Amended estimated amount payable to the contractor (including GST)

$1,992,243.18 (A project to be undertaken)

Any provisions for payment to the contractor for operational or maintenance services
N/A
Method of Tendering

Limited

Description of any provision under which the amount payable to the contractor may be varied
RMS directed additional works or Variations. Annual rate re-negotiations consistent with the Panel Deed, ?There is a formula for cost adjustments in the contract based on indices published by the Australian Bureau of Statistics and other Government bodies.?
Description of any provisions under which the contract may be renegotiated
Nil

Summary of the criteria against which the various tenders were assessed

Evaluation Criteria Weighting
Demonstrated experience in providing commercial advice on works of this type, size and delivery method. Demonstrated experience in providing other technical advice including bridge design, hydrological, noise, project schedule review, financial capacity review, economic evaluation and whole of life costs. Demonstrated capacity to meet the obligations of the NSW Government Policy on Aboriginal Participation in Construction, May 2015 (Updated 1 August 2016), including evidence of previous performance Skills and experience of nominated personnel including CVs. Capacity to provide services. Please provide the percentage of time the nominated personnel would be available for the services. Estimated upper limit, hourly rates for nominated personnel
Contract Contains Agency 'PiggyBack' Clause

No


Industrial Relations Details for this Contract
Name of Sub-contractors (incl. ABN & ACN)
-
Applicable Industrial Instruments
-
Location of Work
-
NSW Industrial Relations inspectors routinely audit the employment records of contractors and sub-contractors to all NSW Government contracts. The results of these inspections are published on the NSW Industrial Relations website.

Agency Contact information@transport.nsw.gov.au

State/Territory NSW

Country AUSTRALIA


Particulars of future transfers of assets to the State, at zero or nominal cost to the State, including the date of their transfer
N/A
Particulars of future transfers of assets to the contractor including the date of their transfer
N/A
The results of any cost-benefit analysis of the contract conducted by the agency
N/A
The components and quantum of the public sector comparator if used
N/A
If relevant, a summary of information used in the contractor's full base case financial model (for example, the pricing formula for tolls or usage charges)
N/A
If relevant, particulars of how risk, during the construction and operational phases of a contract to undertake a specific project (such as construction, infrastructure or property development), is to be apportioned between the parties, quantified (where practicable) in net present-value terms and specifying the major assumptions involved
N/A
Particulars as to any significant guarantees or undertakings between the parties, including any guarantees or undertakings with respect to loan agreements entered into or proposed to be entered into
N/A
Particulars of any other key elements of the contract
Nil