Civil and Electrical work to Principal supplied designs at the Principal’s in service Port Macquarie 132/33kV Substation.
The Contractor shall supply all materials, supervision, labour, plant and other items to complete the work activities listed below, unless specifically identified as being supplied by the Principal under Clause 1.1.6 of the Specification.
Work includes but is not limited to:
- construction of one 132kV line bay,
- construction of two 33kV line bays,
- supply construction and installation of auxiliary equipment and secondary cabling for the line bays and all other associated work required to place the line bays into service.
Location
RFT Type
RFT Preview Document(s)
Additional Details / Instructions
Mandatory Site Inspection is to held on Wednesday 8th September commencing at 11:00am at Port Macquarie Substation located at Thrumster Street Port Macquarie.
Address for Lodgement
As per Part 2 - Conditions of Tendering
Conditions for Participation
In accordance with Clause 1.1.4.1 of the Specification Documents including attandance at the mandatory Site Inspection as per Clause 1.1.11.4.
Estimated Timeframe for Delivery
13 Weeks from Possession of Site