Tender Details
Removal of ten UPSS at five sites across the Southern Ranges Region in Kosciuszko National Park;
- Blowering Works Depot
- Yarrangobilly Caves
- Rules Point
- Lake Jindabyne Works Depot
- Kosciuszko Education Centre
Removal of 1 x AST;
- Yarrangobilly Hydro Plant
Decommissioning in-situ of three UPSS;
- Kiandra
Installation of five AST in three locations;
Lake Jindabyne Works Depot
1 x 15,000 Lt Diesel
1 x 5,000 Lt Unleaded Petrol
Yarrangobilly Caves
1 x 10,000 Lt Diesel
Blowering Works Depot
1 x 10, 000 Lt Diesel
1 x 5,000 Lt Unleaded Petrol)
Location
RFT Type
Tender Respondents
Business Name | Trading Name | Address |
---|---|---|
Air Lube & Lift Services P/L T/as Austank | - | 5 Sonia Street Carrum Downs VIC 3201 AUSTRALIA |
DUROTANK | DUROTANK | 9-15 Grace Street LAKE CARGELLIGO NSW 2672 AUSTRALIA |
Moore Management | Moore Management | 6.09 12 Century Circuit Baulkham Hills NSW 2153 AUSTRALIA |
OTEK Australia P/L | - | Level 4, Suite 4.01 146 Arthur Street North Sydney NSW 2069 AUSTRALIA |
PETRO Industrial (NSW) Pty Ltd | - | C/- Unit 5 / 28 Pritchard Road Virginia QLD 4014 AUSTRALIA |
RMA Contracting Pty Ltd | Ross Mitchell & Associates | 27/6-20 Braidwood St Straithfield NSW 2136 AUSTRALIA |
Synergy Resource Management | - | PO Box 693 North Sydney NSW 2059 AUSTRALIA |
Synergy Resource Management | - | PO Box 693 North Sydney NSW 2059 AUSTRALIA |
The Impax Group | - | 100 Williams Circuit DUBBO NSW 2830 AUSTRALIA |
Additional Details / Instructions
A mandatory pre-tender meeting will be held on the date, at the time and at the place indicated below:
Date: Tuesday 25 October 2011
Meeting Time: 10.30am
Meeting Place: NPWS Office
7a Adelong Road TUMUT NSW
Conduct of Meeting:
10.30 Meet at NPWS Office TUMUT
11.00 Blowering Works Depot
1215 Yarrangobilly Caves
1330 Rules Point
1400 Kiandra
1530 Lake Jindabyne Works Depot
1600 Kosciuszko Education Centre
Address for Lodgement
Estimated Timeframe for Delivery
Item |
Due Date |
Mandatory Site Visits |
25 October 2011 |
Tender Close |
18 November 2011 |
Contract Award |
9 December 2011 |
|
|
Work Completed |
2 March 2012 |