Tender Details
The scope of Works is as follows:
Site 1
· Install replacement culvert 1800 mm diameter, headwalls
· Relocate damaged 1500 mm diameter culvert
· Construct gabion scour protection as detailed on drawings
· Trim and compact road surface
(pipes and headwalls supplied by principal)
Site 2
· Install 2x1200 mm culverts and headwalls (principal supplied pipes and headwalls)
· Reinstatement including compaction of batter and installation of rock to toe of fill including construction of access track
· Reshaping of up slope as detailed in drawing
· Blast/split large boulder upslope of damaged area including construction of access track
· Installation of scour protection (rocks) to channel downstream of culverts
· Trim and compact road surface over culverts and adjacent damaged areas
· Construct rollover on approach to reinstate area
Location
RFT Type
Additional Details / Instructions
A mandatory pre-tender meeting will be held on the date, at the time and at the place indicated below:
Onsite meet at junction of Snowy Mountains Highway and Goobragandra Trail
11:00 am
Thursday 15th December 2011