Parramatta Light Rail (Stage 2) - Infrastructure Technical Advisors (Category 5) - ISD-18-7710B

Contract Award Notice ID ISD-18-7710B
Publish Date 25-Mar-2019
Category Infrastructure
Agency Transport for NSW
Particulars of the goods or services to be provided under this contract

The Infrastructure Technical Advisors (TAs) will be part of the integrated Stage 2 project team developing the definition design to inform the investment decision for FBC2.

The Infrastructure TAs will focus and identify corridor and alignment interfaces, major utilities and structures, environmental constraints and on high risk areas to further define scope, reduce costs, assess constructability.

  • Category 5 — Third Party Utilities (Major) Technical Advisor

This contract has been varied

Original Contract Duration 11-Feb-2019 to 12-Jul-2019
Amended Contract Duration 22-Jul-2021 to 31-Jul-2024

Contract Award Notice Details

Contractor Name Australian Utility Solutions Pty Ltd
ACN 607500685
ABN 22 607 500 685
Is an Aboriginal or Torres Strait Islander owned business No
Street Address Level 22, International Tower 3
Town/City Barrangaroo
State/Territory NSW
Postcode 2000
Country AUSTRALIA


Other private sector entities involved in, with an interest in or benefiting from this contract

Not Applicable

Estimated amount payable to the contractor (including GST)

$528,792.00 (Goods or services supplied)

Amended estimated amount payable to the contractor (including GST)

$2,437,336.00 (Goods or services supplied)

Any provisions for payment to the contractor for operational or maintenance services

Not Applicable

Method of Tendering

Open

Description of any provision under which the amount payable to the contractor may be varied

 

Any variations, options and extensions of time required by the Principal valued in accordance with Clause 16 - Variations and Clause 18 - Time

Description of any provisions under which the contract may be renegotiated

Not Applicable


Summary of the criteria against which the various tenders were assessed

Evaluation Criteria Weighting

1. Tenderer's Relevant Project Experience and Current/Future Workload

10%

2. Tenderer's Understanding of the Services and Methodology for the Project

30%

3. Tenderer's Project Organisational Structure, Key Resources and Availability

30%

4. Fee Proposal

30%
Contract Contains Agency 'PiggyBack' Clause

No


Industrial Relations Details for this Contract
Name of Sub-contractors (incl. ABN & ACN)

Not Applicable

Applicable Industrial Instruments

Not Applicable

Location of Work

Not Applicable

NSW Industrial Relations inspectors routinely audit the employment records of contractors and sub-contractors to all NSW Government contracts. The results of these inspections are published on the NSW Industrial Relations website.

Agency Contact Attn: Project Information Officer, Infrastructure and Place, TfNSW

State/Territory NSW

Country AUSTRALIA

Other Information

Original contract sum of $480,720 exl GST and Date for Completion of 12/7/2021

This contract has been varied:

  • Variation 01: an addtional $447,200 excl GST and revised Date for Completion of 17/12/2021 - (Adjusted initial engagement expenditure - $380.920)
  • Variation 02: revised Date for Completion of 30/6/2022 
  • Variation 03: an addtional $659,720 excl GST and revised Date for Completion of 31/8/2022
  • Variation 04: revised Date for Completion of 31/05/2023
  • Variation 05: an addtional $648,200 excl GST and revised Date for Completion of 31/3/2024
  • Variation 06: an addtional $79,720 excl GST and revised Date for Completion of 31/7/2024