Sydney Metro City and Southwest - Sydenham Station and Junction Works - CW2291132

Contract Award Notice ID CW2291132
Publish Date 7-Sep-2018
Category Roads and rail
Agency Transport NSW - Corporate
Particulars of the goods or services to be provided under this contract

The SSJ Project is an upgrade of existing rail systems at Sydenham to allow for Sydney Metro railway.  

• The reconfiguration of existing track and rail systems to segregate the Sydney Trains T3 Bankstown Line and the goods line,

• Installation of Sydney Metro rail systems (including crossover and turn-back facilities), upgrading of Platforms 1 and 2 to Sydney Metro standards and construction of two new station entrances at Burrows Road and Railway Parade,

• Erection of a new second concourse over the station with lifts and stairs to each platform. And straightening of the Sydney Metro platforms and platform screen doors 

• Improved interchanges between Sydney Trains & Metro services and to bus connections, and adjustments to the Sydenham Pit and Drainage Pumping Station  

Original Contract Duration 20-Sep-2017 to 3-Dec-2021
Amended Contract Duration 1-Jul-2022 to 24-Aug-2024

Contract Award Notice Details

Contractor Name John Holland Pty Ltd Laing O'Rourke Australia Construction Pty Ltd
ACN 583317803
ABN 73 583 317 803
Is an Aboriginal or Torres Strait Islander owned business No
Street Address L12/ 4-6 Bligh St
Town/City Sydney
State/Territory NSW
Postcode 2000
Country AUSTRALIA


Other private sector entities involved in, with an interest in or benefiting from this contract

Not Applicable

Estimated amount payable to the contractor (including GST)

$301,204,275.37 (A project to be undertaken)

Amended estimated amount payable to the contractor (including GST)

$1,168,056,235.00 (A project to be undertaken)

Any provisions for payment to the contractor for operational or maintenance services

Not Applicable

Method of Tendering

Multi-Stage

Description of any provision under which the amount payable to the contractor may be varied

As described in the Contract

Description of any provisions under which the contract may be renegotiated

As amended by written agreement


Summary of the criteria against which the various tenders were assessed

Evaluation Criteria Weighting

N/A

Contract Contains Agency 'PiggyBack' Clause

No


Industrial Relations Details for this Contract
Name of Sub-contractors (incl. ABN & ACN)

Refer to Schedule A1 - Contract Particulars

Applicable Industrial Instruments

Not Applicable

Location of Work

Sydenham Station and Junction

NSW Industrial Relations inspectors routinely audit the employment records of contractors and sub-contractors to all NSW Government contracts. The results of these inspections are published on the NSW Industrial Relations website.

Agency Contact Sam Field

Phone Number 02 8265 6280


Particulars of future transfers of assets to the State, at zero or nominal cost to the State, including the date of their transfer

Not Applicable

Particulars of future transfers of assets to the contractor including the date of their transfer

Not Applicable

The results of any cost-benefit analysis of the contract conducted by the agency

Refer to the City & Southwest final business case

The components and quantum of the public sector comparator if used

Refer to the City & Southwest final business case

If relevant, a summary of information used in the contractor's full base case financial model (for example, the pricing formula for tolls or usage charges)

Refer to the City & Southwest final business case

If relevant, particulars of how risk, during the construction and operational phases of a contract to undertake a specific project (such as construction, infrastructure or property development), is to be apportioned between the parties, quantified (where practicable) in net present-value terms and specifying the major assumptions involved

Risk allocation is set out in the Commercial Framework and Contract

Particulars as to any significant guarantees or undertakings between the parties, including any guarantees or undertakings with respect to loan agreements entered into or proposed to be entered into

Specific guarantees and undertakings are set out in the Contract

Particulars of any other key elements of the contract

Particulars of key elements are set out in the Contract

A web site address which provides direct access to the complete contract less confidential information
Has the contract or any provisions within it been withheld from this disclosure under the exemptions provisions of the GIPA Act Section 32? (YES or NO)
Yes
If yes to the above, what are the reasons why the contract, or provisions therein, have not been provided?

Yes

If yes to the above, is it intended that the contract or those provisions be published at a later date, and if so, when?

No

If yes to the above, when some but not all provisions of the contract have been published, a general description of the types of provisions that have not been provided

Yes