Parramatta Light Rail - Independent Probity Advisor - ISD-16-5879

Contract Award Notice ID ISD-16-5879
Publish Date 4-May-2017
Category Professional Services (excl Consultancies)
Agency Transport for NSW
Particulars of the goods or services to be provided under this contract

The Independent Probity Advisor Services for the Parramatta Light Rail Project will provide Services as follows: 

• prepare a project specific probity plan for the Parramatta Light Rail Project which captures the procurement of both professional services contracts and major works package(s)

• review the Invitation to Tender and Addendum documents from a probity perspective and provide advice if necessary 

•  provide advice on the management of confidentiality and conflicts of interest

• review and provide advice on TfNSW probity strategies 

• carry out audits of other professional services contractor to ensure compliance with the probity requirements

• investigate and report on any suspect or actual probity breaches relating to the Parramatta Light Rail Project

 

Original Contract Duration 6-Mar-2017 to 30-Jun-2019
Amended Contract Duration 6-Nov-2018 to 30-Jun-2024

Contract Award Notice Details

Contractor Name Procure Group Pty Ltd
ACN 130908824
ABN 22 130 908 824
Is an Aboriginal or Torres Strait Islander owned business No
Street Address GPO Box 1104 Sydney NSW 2001
Town/City Sydney
State/Territory NSW
Postcode 2001
Country AUSTRALIA


Related RFT ID
ISD-16-5879


Other private sector entities involved in, with an interest in or benefiting from this contract

Not Applicable

Estimated amount payable to the contractor (including GST)

$287,760.00 (Goods or services supplied)

Amended estimated amount payable to the contractor (including GST)

$756,536.00 (Goods or services supplied)

Any provisions for payment to the contractor for operational or maintenance services

Not Applicable

Method of Tendering

Limited

Description of any provision under which the amount payable to the contractor may be varied

Clause 12 Variations (services and/or timing). There is two Options to this Contract for the period of engagement

Description of any provisions under which the contract may be renegotiated

Not Applicable


Summary of the criteria against which the various tenders were assessed

Evaluation Criteria Weighting

As below:

As below

Fee (Tender Schedule 2)

30

Qualifications and recent experience of the Tenderer's nominated personnel in undertaking similar services on similar signicant projects of value in excess of $500 million (Tender Schedule 10) 

40

Tenderer's understanding of the scope of services, the methodology and the key risks in performing the independent probity advisor services for the Parramatta Light Rail Project (Tender Schedule 9)

30
Contract Contains Agency 'PiggyBack' Clause

No


Industrial Relations Details for this Contract
Name of Sub-contractors (incl. ABN & ACN)

Not Applicable

Applicable Industrial Instruments

Not Applicable

Location of Work

Not Applicable

NSW Industrial Relations inspectors routinely audit the employment records of contractors and sub-contractors to all NSW Government contracts. The results of these inspections are published on the NSW Industrial Relations website.

Agency Contact TfNSW - Infrastructure and Services - Attn: Project Information Officer

Street Address Level 5, Tower A, Zenith Centre, 821 Pacific Highway

Town/City Chatwood

State/Territory NSW

Postcode 2067

Country AUSTRALIA

Phone Number 02 9200 0200

Other Information

The disclosed contractvalue represents the cumulative contract price of all engagements, including variations (if applicable), plus and additional 10% for GST. This value may be overstated if GST not apply to (all parts of) the Contract

The Contract has been varied:

Original Contract value of $287,760 (excl. GST) and a completion Date of 30 June 2017

Option 1 - additional $809,760 (excl. GST) and a revised Completion Date of 31 December 2018

Variation 1 - 5 - Nil

Variation 6 - an ommision -$352,130 and revised Completion Date of 31 December 2022

Variation 7 - Nil and revised Completion Date of 31 Decemebr 2023

Variation 8 - Nil and revised Completion Date of 30 June 2024