Contract Award Notice Details
Contractor Name Cubic Transportation Systems
ACN 003617561
ABN
82 003 617 561
Is an Aboriginal or Torres Strait Islander owned business No
Street Address Level 23, 477 Pitt Street
Town/City SYDNEY
State/Territory NSW
Postcode 2000
Country AUSTRALIA
Other private sector entities involved in, with an interest in or benefiting from this contract
Estimated amount payable to the contractor (including GST)
$82,500,000.00 (Goods or services supplied)
Amended estimated amount payable to the contractor (including GST)
$96,444,019.00 (Goods or services supplied)
Any provisions for payment to the contractor for operational or maintenance services
Description of any provision under which the amount payable to the contractor may be varied
Provision from T&M costs related to Data Cleansing and MIgration services. Additionally, the contract contains provisions which permit the parties to agree variations to the scope of work, including mechanisms for adjusting the amounts payable to the contract under the contract accordingly
Description of any provisions under which the contract may be renegotiated
Summary of the criteria against which the various tenders were assessed
Evaluation Criteria |
Weighting |
In relation to the Request for Proposals (RFP), the TfNSW Tender Evaluation Committee conducted a comparative quantitative and qualitative evaluation of proposals against the following broad evaluation criteria: 1. Willingness to do business 2. Integration, Partnership and Innovation 3. Suitability of the Proposed Solution 4. Organisational Capability 5. Price |
|
|
Contract Contains Agency 'PiggyBack' Clause
Industrial Relations Details for this Contract
Name of Sub-contractors (incl. ABN & ACN)
Mentz GmbH - ABN 55 324 460 573
WSP Australia Pty Ltd - ABN 80 078 004 798
PTV Asia Pacific Pty Ltd - ABN 83 108 021 263
Applicable Industrial Instruments
NSW Industrial Relations inspectors routinely audit the employment records of contractors and sub-contractors to all NSW Government contracts. The results of these inspections are published on the NSW Industrial Relations website.
Particulars of future transfers of assets to the State, at zero or nominal cost to the State, including the date of their transfer
Particulars of future transfers of assets to the contractor including the date of their transfer
The results of any cost-benefit analysis of the contract conducted by the agency
TfNSW undertook appropriate economic and financial analyses which concluded the ECTMS proposal had a positive cost-benefit ratio.
The components and quantum of the public sector comparator if used
If relevant, a summary of information used in the contractor's full base case financial model (for example, the pricing formula for tolls or usage charges)
If relevant, particulars of how risk, during the construction and operational phases of a contract to undertake a specific project (such as construction, infrastructure or property development), is to be apportioned between the parties, quantified (where practicable) in net present-value terms and specifying the major assumptions involved
Particulars as to any significant guarantees or undertakings between the parties, including any guarantees or undertakings with respect to loan agreements entered into or proposed to be entered into
Parent Company Guarantee provided by Cubic Corporation. In addition, the contractor is required to provide certain Security Bonds to TfNSW.
Particulars of the Parent Company Guarantee and Security Bonds have not been disclosed due to this being commercial-in-confidence information of the contractor.
Particulars of any other key elements of the contract
Refer to contract (separately disclosed).
A web site address which provides direct access to the complete contract less confidential information
Has the contract or any provisions within it been withheld from this disclosure under the exemptions provisions of the GIPA Act Section 32? (YES or NO)
Yes
If yes to the above, what are the reasons why the contract, or provisions therein, have not been provided?
This information cannot be disclosed as it contains commercial-in-confidence information of the contractor.
If yes to the above, is it intended that the contract or those provisions be published at a later date, and if so, when?
If yes to the above, when some but not all provisions of the contract have been published, a general description of the types of provisions that have not been provided
Certain provisions of the contract have not been disclosed as permitted under section 32 of the Government Information (Public Access) Act 2009 (NSW). The remainder of the contract has been published. |