More Trains, More Services Stage 3A (MTMS3A) - Sydney Terminal Area Reconfiguration Phase 2 (STAR 2) Package of Works - IPD-19-8197-008

Contract Award Notice ID IPD-19-8197-008
Publish Date 8-Mar-2023
Category Infrastructure
Agency Transport for NSW
Particulars of the goods or services to be provided under this contract

The Incentivised Delivery Entity (IDE) will deliver the Sydney Terminal Area Reconfiguration Phase 2 (STAR 2) package of works for More Trains, More Services Stage 3A (MTMS3A).

The scope of works comprises of track, signalling, overhead power and station platform modifications within the Sydney Terminal area to improve efficiency of train movements to and from platforms 9 to 14 and the deployment of the Mariyung Fleet.

The Target Outturn Cost (TOC) has since been adjusted due to cost impacts relating to:

  • Chullora Electrical Learning Centre.
Contract Duration 20-Dec-2022 to 16-Jun-2025

Contract Award Notice Details

Contractor Name Transport for Tomorrow (Laing O'Rourke Australia Construction Pty Ltd and Kellogg Brown & Root Pty Ltd)
ACN 351239872
ABN 58 351 239 872
Is an Aboriginal or Torres Strait Islander owned business No
Street Address Level 21, 100 Mount Street
Town/City North Sydney
State/Territory NSW
Postcode 2060
Country AUSTRALIA


Related RFT ID
ISD-18-7764


Other private sector entities involved in, with an interest in or benefiting from this contract

Transport for Tomorrow (Laing O’Rourke Australia Construction Pty Ltd and Kellogg Brown & Root Pty Ltd

Estimated amount payable to the contractor (including GST)

$152,089,513.40 (A project to be undertaken)

Amended estimated amount payable to the contractor (including GST)

$152,214,412.22 (A project to be undertaken)

Any provisions for payment to the contractor for operational or maintenance services

Not Applicable

Method of Tendering

Non Tender

Description of any provision under which the amount payable to the contractor may be varied

TfNSW Incentivised Delivery Agreement (IDA):

• Clause 20.3–20.7 Target Adjustment Events

• Clause 21.8 Set-off, withholding and reduction

• Clause 27 Termination or step in

• Schedule 7 Compensation Framework — ‘Reimbursable Costs’, ‘Fee’ & ‘Gainshare/Painshare Regimes’

Description of any provisions under which the contract may be renegotiated

Not Applicable


Contract Contains Agency 'PiggyBack' Clause

No


Industrial Relations Details for this Contract
Name of Sub-contractors (incl. ABN & ACN)

Not Applicable

Applicable Industrial Instruments

Not Applicable

Location of Work

Not Applicable

NSW Industrial Relations inspectors routinely audit the employment records of contractors and sub-contractors to all NSW Government contracts. The results of these inspections are published on the NSW Industrial Relations website.

Agency Contact Attn: Project Information Officer, Infrastructure and Place, TfNSW

State/Territory NSW

Country AUSTRALIA

Other Information

The More Trains, More Services Stage 3A (MTMS3A) – STAR 2 package of works has been issued to the IDE as an Additional Project under Incentivised Delivery Agreement (IDA) IPD-19-8197*.

Project Proposal Phase

The IDE was instructed to begin Project Definition Services (PDS) for this project pursuant to Clause 11.1(a)(ii) of the IDA.

Early Execution Works Phase

Early Execution Works (EEW) were issued to the IDE pursuant to Clause 13 of the IDA with an Expenditure Limit of $10,000,000 (excl. GST).

Project Execution Phase

The Project Proposal was accepted in accordance with Clause 12 of the IDA. The Target Outturn Cost (TOC) of $138,263,194 (excl. GST) for this project is inclusive of EEW.

Target Adjustment Events

The TOC has been adjusted as follows:

Target Adjustment Event 01: an additional $113,544.38 (excl. GST)

The disclosed value represents the cumulative expenditure limit for all engagements plus an additional 10% for GST. This value may be overstated if GST does not apply to [all parts of] the contract.

*IPD-19-8197 was awarded following a multi-stage tender process and has been disclosed separately under the Contract Award Notice for IPD-19-8197.