More Trains, More Services (MTMS) Stage 2 – Signalling Detailed Design - Package 2 - IPD-19-8035B

Contract Award Notice ID IPD-19-8035B
Publish Date 20-Dec-2019
Category Professional Services (excl Consultancies)
Agency Transport for NSW
Particulars of the goods or services to be provided under this contract

The provision of signalling design services for Package 2 – Waterfall Stabling Facility.

This engagement has since been varied as follows:

  • signalling design for the new bogie exchange system at Mortdale Maintenance Centre;
  • Automatic Train Protection (ATP) trackside and data design;
  • design alterations;
  • Independent Reviewer to comply with TfNSW Judgement of Significance (JoS) assessment; 
  • Asset Standards Authority (ASA) change impacts;
  • Feasibility Study; 
  • Additional design and resequencing;
  • COVID delays and disruption to the Waterfall Signalling program;
  • Signal Sighting activities on WE28 8-Jan-2022;
  • Impact to PINK copy circuit books CB280 and CB069K along with re-work on the CB069 removal books;
  • Cable rack 2 not installed in WE42. This affects both Stage 9 and Signals Package;
  • W79 & W1 Signal Install and commission (from ESI scope);
  • 312 Points installed with temporary detection (from Stage 9 scope);
  • Updates to the control and indication panel; and
  • PIA delays and disruption to the Waterfall Signalling program and changes to detailed designs.
Original Contract Duration 21-Nov-2019 to 30-Oct-2022
Amended Contract Duration 21-Nov-2019 to 31-Oct-2024

Contract Award Notice Details

Contractor Name JMD Railtech Engineering Pty Ltd
ACN 133769918
ABN 44 133 769 918
Is an Aboriginal or Torres Strait Islander owned business No
Street Address Level 3, 263 Clarence St
Town/City Sydney
State/Territory NSW
Postcode 2000
Country AUSTRALIA


Related RFT ID
IPD-19-8035


Other private sector entities involved in, with an interest in or benefiting from this contract

Not Applicable

Estimated amount payable to the contractor (including GST)

$3,008,214.31 (Goods or services supplied)

Amended estimated amount payable to the contractor (including GST)

$5,893,825.38 (Goods or services supplied)

Any provisions for payment to the contractor for operational or maintenance services

Not Applicable

Method of Tendering

Open

Description of any provision under which the amount payable to the contractor may be varied

TfNSW Professional Services Contract (PSC):

  • Clause 16 Variations
  • Clause 17.5 Set Off
  • Clause 18.3 Extension of time
  • Clause 18.8 Suspension
  • Clause 21 Termination
 
Description of any provisions under which the contract may be renegotiated

Not Applicable


Summary of the criteria against which the various tenders were assessed

Evaluation Criteria Weighting

Expertise and experience of the Tenderer's key personnel, availability and allocation to the project and its project organisational structure

40

Fee Proposal 

30

Tenderer's program and resourcing allocation and its demonstration of how the milestones will be achieved

10

Tenderer's proposed design methodology and its understanding of the package and services

20
Contract Contains Agency 'PiggyBack' Clause

No


Industrial Relations Details for this Contract
Name of Sub-contractors (incl. ABN & ACN)

Not Applicable

Applicable Industrial Instruments

Not Applicable

Location of Work

Not Applicable

NSW Industrial Relations inspectors routinely audit the employment records of contractors and sub-contractors to all NSW Government contracts. The results of these inspections are published on the NSW Industrial Relations website.

Agency Contact Attn: Project Information Officer, Infrastructure and Place, TfNSW

State/Territory NSW

Country AUSTRALIA

Other Information

The Contractor is a member of the NSW Government's Prequalification Scheme: SCM0005 Performance and Management Services and has been engaged under the TfNSW Professional Services Contract (PSC).

Original contract price: $2,734,740.28 (excl. GST)
Original contract end date: 30-Oct-2021

This contract has been varied.

  • Variation 01: an additional $34,978.00 (excl. GST)
  • Variation 02: an additional $1,832,371.84 (excl. GST)
  • Variation 03: an additional $50,312.00 (excl. GST)
  • Variation 04: an additional $42,053.00 (excl. GST)
  • Variation 05: an additional $45,030.00 (excl. GST)
  • Variation 06: an additional $120,000.00 (excl. GST)
  • Variation 07: an additional $51,634.00 (excl. GST)
  • Variation 08: an additional $22,742.00 (excl. GST) and revised Date for Completion of 30-Oct-2022
  • Variation 09: N/A
  • Variation 10: an additional $99,092.72 (excl. GST)
  • Variation 11: an additional $287,952.85 (excl. GST)
  • Variation 12: revised Date for Completion of 31-Oct-2023
  • Variation 13: an additional $37,116.38 (excl. GST)
  • Variation 14: revised Date for Completion of 31-Oct-2024

The disclosed contract value represents the cumulative contract price of all engagements, including variations (if applicable), plus an additional 10% for GST.  This value may be overstated if GST does not apply to [all parts of] the contract.