Regional Rail Project - Design and Construction of Moss Vale Station and Stabling Yard Upgrade - ISD-18-7781L

Contract Award Notice ID ISD-18-7781L
Publish Date 7-Mar-2023
Category Infrastructure
Agency Transport for NSW
Particulars of the goods or services to be provided under this contract

The Contractor will complete the Design and Construction of the Moss Vale Station (MSS) (SP1) and Moss Vale Stabling Yard Upgrade (MVSY) (SP2).

This contract has been varied, to include:

  • Exercise of Option 5
  • Additional drainage Investigation
  • Supply, install and commissioining Lift #3
  • Construction of Argyle St Entrance.
Original Contract Duration 2-Mar-2023 to 9-Jul-2025
Amended Contract Duration 2-Mar-2023 to 6-Aug-2025

Contract Award Notice Details

Contractor Name Degnan Constructions Pty Ltd
ACN 001745348
ABN 11 001 745 348
Is an Aboriginal or Torres Strait Islander owned business No
Street Address 50 Barry Avenue
Town/City Mortdale
State/Territory NSW
Postcode 2223
Country AUSTRALIA


Other private sector entities involved in, with an interest in or benefiting from this contract

Not Applicable

Estimated amount payable to the contractor (including GST)

$55,528,083.60 (A project to be undertaken)

Amended estimated amount payable to the contractor (including GST)

$69,396,660.89 (A project to be undertaken)

Any provisions for payment to the contractor for operational or maintenance services

Not Applicable

Method of Tendering

Non Tender

Description of any provision under which the amount payable to the contractor may be varied

TfNSW Medium Works Contract:

  • Clause 6 - Variations
  • Schedule 10 - Prices and Rates for valuation of Variations and Overhead Costs.
Description of any provisions under which the contract may be renegotiated

Not Applicable


Summary of the criteria against which the various tenders were assessed

Evaluation Criteria Weighting

1. Technical Assessment

2. Commercial Assessment including Value for Money

3. Assessment by Independent Estimator

Contract Contains Agency 'PiggyBack' Clause

No


Industrial Relations Details for this Contract
Name of Sub-contractors (incl. ABN & ACN)

Not Applicable

Applicable Industrial Instruments

Not Applicable

Location of Work

Not Applicable

NSW Industrial Relations inspectors routinely audit the employment records of contractors and sub-contractors to all NSW Government contracts. The results of these inspections are published on the NSW Industrial Relations website.

Agency Contact Attn: Project Information Officer, Infrastructure and Place, TfNSW

State/Territory NSW

Country AUSTRALIA

Other Information

This TfNSW Medium Works Contract has been awarded under the existing Station Upgrades Framework Deed ISD-18-7781* with Degnan Constructions Pty Ltd which was executed on 27 June 2019 and has been disclosed separately.

The Principal can accept a Quotation submitted by the Contractor under clause 1.2 of the Annexure B to Framework Deed ISD-18-7781 by issuing a Notice to Proceed letter to the Contractor.

TfNSW accepted a quotation submitted by the Contractor for the  upgrade under clause 1.2 Annexure B to the Framework Deed ISD-18-7781 which was assessed as per the above mentioned evaluation criteria.

* ISD-18-7781 was procured through the following two (2) stages:

Stage 1: Expression of Interest (EOI) short listed seven (7) successful Applicants.

Stage 2: Three (3) of the Applicants who were short listed through the EOI process were invited to provide a submission in response to an Invitation to Tender (ITT).

One (1) successful Applicant (the Contractor) was then selected to execute a contractual agreement comprising a Framework Deed to Design and Construct Station Upgrades for the Transport Access Program Tranche 3 (TAP 3) and two (2) Design and Construct contracts for the Mittagong Station Upgrade and Fairy Meadow Station Upgrade. The Mittagong Station Upgrade and Fairy Meadow Station Upgrade and any new Design and Construct contracts awarded under the Framework Agreement are disclosed separately.

This contract has been varied:

  • Variation 01/Option 5: an additional $426,000 (excl. GST)
  • Variation 02: an additional $260,472.50 (excl. GST)
  • Variation 03: an additional $261,606.00 (excl. GST)
  • Variation 04: Pending 
  • Variation 05 (V6): an additional $1,116,438.40 (excl. GST)
  • Variation 06 (V5): an additional $20,874.92 (excl. GST)
  • Variation 12 (V6): a reduction of $382,853.41 (excl. GST)
  • Variation 16 (V8): an additional $25,102.50 (excl. GST)
  • Variation 17 (V7): an additional $323,965.32 (excl. GST)
  • Option 01: an additional $4,578,850 (excl. GST)
  • Option 02: an additional $1,518,816 (excl. GST)
  • Option 03: an additional $304,040 (excl. GST)
  • Option 04: an additional $695,194 (excl. GST)
  • Option 06: an additional $578,475 (excl. GST)
  • Extension of Time: revised Date for Completion of 6-Aug-2025
  • Variation 07: an additional $1,188,190.17 (excl. GST)

The disclosed contract value represents the cumulative contract price of all engagements, including variations (if applicable), plus an additional 10% for GST. This value may be overstated if GST does not apply to [all parts of] the contract.