Tender Details
The Barangaroo Headland Park Sewerage and Stormwater Diversion Works Request for Tender is a key part of the delivery strategy for the Barangaroo precinct.
The Barangaroo Delivery Authority is seeking Tenders from the construction sector for the Sewerage and Strormwater Diversion Works and Operation & Maintenance Services within the public domain at Barangaroo Headland Park.
The Works and Services are generally:
- Construction of a new sewerage services;
- Construction of a temporary sewerage bypass pumping scheme on Hickson Road;
- Decommission existing sewerage services on the Headland Park site;
- Deviation of existing stormwater services on the Headland Park site; and
- Operation and Maintenance of the Temporary Sewerage Bypass 2012.
Location
Estimated Value
RFT Type
RFT Preview Document(s)
Related Web Site Address
Tender Respondents
Business Name | Trading Name | Address |
---|---|---|
AJ Lucas | - | Suite 204, 147 Gordon St Port Macquarie NSW 2444 AUSTRALIA |
Athassel Excavations Pty Ltd | - | 51 Carrington Rd Randwick NSW 2031 AUSTRALIA |
Killard Excavation Pty Ltd | - | Unit 10, 287 Victoria Rd Rydalmere NSW 2116 AUSTRALIA |
Reed Constructions Australia | - | Level 3, 41 McLaren St North Sydney NSW 2060 AUSTRALIA |
Trazlbat Pty Ltd | A/A | 57 Churchill ave Strathfield NSW 2135 AUSTRALIA |
Related Records
- Contract Award Notices:
- BDA-CAN-03 Killard Excavation Pty Limited
Additional Details / Instructions
Site Inspection Tuesday 5 October 2010 2.00pm
EMAIL RSVP to Contact person
Gate 3, Barangaroo Precinct
cnr Towns Place, Millers Point
Sydney, 2000
Address for Lodgement
Conditions for Participation
Contractors must be accredited, of capable or engaging accredited, Sydney Water contractors in the following categories:
W1 |
Water Reticulation DN 100-375 |
|
|
S1 |
Sewerage Reticulation DN 150-300 |
W2 |
Water Supply DN > 375-750 |
S2 |
Sewer Standard DN 375-750 |
PE |
PE Pipe Systems |
Estimated Timeframe for Delivery
Works to commence on site: beginnnig of November 2010
Works to reach practical completion: end of January 2011
Operational and Maintenance services period finishes: : early 2012