Tender Details
Council is seeking tenders from suitably qualified and experienced contractor to undertake Crest Sporting Complex Stormwater Harvesting & Reuse Project
The main component of the works under this Contract generally includes:
· Stormwater diversion pipeline 1
· Stormwater diversion pipeline 2
· Gross pollutant trap
· Bioretention System
· Expanded Storage Pond
· Stormwater supply to irrigation system
· Post Storage treatment
Location
RFT Type
Related Records
- Contract Award Notices:
- T39-10 Antoun Civil Engineering (Aust) Pty Ltd
Additional Details / Instructions
There will be a mandatory tender briefing on Thursday 26/08/2010 @ 10:00am on site
The exact location of the site meeting for the mandatory tender briefing on 26/08/2010 at 10:00 am is Carrysfield Road carpark, next to the location of proposed CDS unit.
Failure to attend the above meeting shall lead to no further consideration of the tender submission.
Works are anticipated to start on 18 October 2010 with 14 week construction duration. Scheduled Practical completion shall be reached by
7th February 2011. This period excludes the period between 20/12/2010 and 02/01/2011.