More Trains, More Services (MTMS) Stage 2 - Signalling Detailed Design - Package 3 - IPD-19-8362A

Contract Award Notice ID IPD-19-8362A
Publish Date 20-Dec-2019
Category Professional Services (excl Consultancies)
Agency Transport for NSW
Particulars of the goods or services to be provided under this contract

The Professional Services Contractor is required to provide signalling design services for Hurstville Crossover and T8 transformation as part of Package 3.

The contract has since been varied, including:

  • engagement of a third party for data design, testing and commissioning support for Smartlock works at Hurstville
  • Automatic Selective Door Opening (ASDO) system implementation at Central Station
  • cost impacts relating to Wolli Creek air gap relocation
  • additional interim stage works
  • Design Integrity Testing (DIT) cost impacts relating to signal relocation
  • engagement of a third party for incorporation of ATP data into balises for the Wolli creek air gap portion of works
  • industrial action impacts.
Original Contract Duration 5-Dec-2019 to 31-May-2022
Amended Contract Duration 5-Dec-2019 to 30-Apr-2024

Contract Award Notice Details

Contractor Name WSP Australia Pty Ltd
ACN 078004798
ABN 80 078 004 798
Is an Aboriginal or Torres Strait Islander owned business No
Street Address Level 27, 680 George Street
Town/City Sydney
State/Territory NSW
Postcode 2000
Country AUSTRALIA


Related RFT ID
IPD-19-8362


Other private sector entities involved in, with an interest in or benefiting from this contract

Not Applicable

Estimated amount payable to the contractor (including GST)

$2,113,606.55 (Goods or services supplied)

Amended estimated amount payable to the contractor (including GST)

$6,247,732.88 (Goods or services supplied)

Any provisions for payment to the contractor for operational or maintenance services

Not Applicable

Method of Tendering

Open

Description of any provision under which the amount payable to the contractor may be varied

TfNSW Professional Services Contract (PSC):

• Clause 16 Variations

• Clause 17.5 Set Off

• Clause 18.3 Extension of Time

• Clause 18.8 Suspension

• Clause 21 Termination

 

Description of any provisions under which the contract may be renegotiated

Not Applicable


Summary of the criteria against which the various tenders were assessed

Evaluation Criteria Weighting

Expertise and experience of the Tenderer's key personnel, availability and allocation to the project and its project organisational structure

40

Fee Proposal

30

Tenderer's program and resourcing allocation and its demonstration of how the milestones will be achieved

20

Tenderer's proposed design methodology and its understanding of the package and services

10
Contract Contains Agency 'PiggyBack' Clause

No


Industrial Relations Details for this Contract
Name of Sub-contractors (incl. ABN & ACN)

Not Applicable

Applicable Industrial Instruments

Not Applicable

Location of Work

Not Applicable

NSW Industrial Relations inspectors routinely audit the employment records of contractors and sub-contractors to all NSW Government contracts. The results of these inspections are published on the NSW Industrial Relations website.

Agency Contact Attn: Project Information Officer, Infrastructure and Place, TfNSW

State/Territory NSW

Country AUSTRALIA

Other Information
The Contractor is a member of the NSW Government's Prequalification Scheme: SCM0005 Performance and Management Services and has been engaged under the TfNSW Professional Services Contract (PSC)
 
Original contract price: $1,921,460.50  (excl. GST).
Original contact end date: 31-May-2022

The TfNSW Professional Services contract has been varied:

  • Variation 01: an additional $696,142.57 (excl. GST) 
  • Variation 02: an additional $275,209.88 (excl. GST) 
  • Variation 03: an additional $160,030.93 (excl. GST) 
  • Variation 04: an additional $63,174.52 (excl. GST) 
  • Variation 05: an additional $53,599.36 (excl. GST) 
  • Variation 06: an additional $470,000.16 (excl. GST) 
  • Variation 07: an additional $96,793.37 (excl. GST) 
  • Variation 08: an additional $419,545.28 (excl. GST) 
  • Variation 09: an additional $372,893.72 (excl. GST)
  • Variation 10 & 11: an additional $67,266.24 (excl. GST)
  • Variation 12: an additional $330,253.52 (excl. GST)
  • Variation 13: an additional $366,023.02 (excl. GST) and revised Date for Completion of 31-Mar-2023
  • Variation 14: an additional $206,816.39 (excl. GST)
  • Variation 15: an additional $12,125.02 (excl. GST)
  • Variation 16: an additional $168,422.68 (excl GST) and revised Date for Completion of 30-Apr-2024

The disclosed contract value represents the cumulative contract price of all engagements, including variations (if applicable), plus an additional 10% for GST.  This value may be overstated if GST does not apply to [all parts of] the contract.